America's energy crisis is hiding in plain sight and it's worse than you know

  • Welcome to Christian Forums, a Christian Forum that recognizes that all Christians are a work in progress.

    You will need to register to be able to join in fellowship with Christians all over the world.

    We hope to see you as a part of our community soon and God Bless!

Scott Downey

Well-Known Member
Dec 19, 2021
7,926
4,949
113
65
St. Thomas
Faith
Christian
Country
Virgin Islands, U.S.
Trump's national emergency declaration is real about modernizing the electric grid
Future electrical demand is going to skyrocket.



America’s electrical grid is in desperate need of investment and modernization. Built largely in the 1960s and 70s it struggles to meet today’s demands for reliability and resilience—let alone the exponential growth expected from new technologies like artificial intelligence, quantum computing, and potentially fusion energy. Power outages are becoming more frequent and severe, as aging infrastructure buckles under the strain of extreme weather events and rising consumption.
 

Rockerduck

Well-Known Member
Nov 7, 2022
2,300
1,978
113
70
Marietta, Georgia.
Faith
Christian
Country
United States
Every time we have had a national disaster, the electric wires, poles, and transformers have all been replaced. I have often said "why don't they bury the cables", but power companies just put up the same poles and pull new wire. All local municipalities are responsible for upgrading sewer, water, and local power companies are responsible for Power. All this through taxes people pay. This is not the Federal govt job. I retired from local govt. That's why power companies from other localities arrive to assist in disasters. It's not the Fed. If an area is not upgraded, it lies in the local govt's lap.
 

Jack

Well-Known Member
May 3, 2022
11,186
4,608
113
Midwest
Faith
Christian
Country
United States
Every time we have had a national disaster, the electric wires, poles, and transformers have all been replaced. I have often said "why don't they bury the cables", but power companies just put up the same poles and pull new wire. All local municipalities are responsible for upgrading sewer, water, and local power companies are responsible for Power. All this through taxes people pay. This is not the Federal govt job. I retired from local govt. That's why power companies from other localities arrive to assist in disasters. It's not the Fed. If an area is not upgraded, it lies in the local govt's lap.
And why don't they bury homes? At least partially. That might upset the power companies. $$$
 
  • Like
Reactions: talons

bluedragon

Well-Known Member
Aug 7, 2021
2,122
1,591
113
70
Birmingham, Al
Faith
Christian
Country
United States
Every time we have had a national disaster, the electric wires, poles, and transformers have all been replaced. I have often said "why don't they bury the cables", but power companies just put up the same poles and pull new wire. All local municipalities are responsible for upgrading sewer, water, and local power companies are responsible for Power. All this through taxes people pay. This is not the Federal govt job. I retired from local govt. That's why power companies from other localities arrive to assist in disasters. It's not the Fed. If an area is not upgraded, it lies in the local govt's lap.
Neither of you ever worked in the power industry did you? Your opinions are honestly uninformed. Every opportunity is used to upgrade apparatus when it's necessary. For the most part, the public is paying the freight for the updating. Manufacturers abandoned old poor performing technology for far superior modern technology. Want to get your eyes opened? Walk into a government power producing or distributing meeting and present what's available today The engineers will look at you like they were dropped in from a Flintstones episode. Large transformers are designed and intended to operate for 50 plus years.

Best advice is to stop listening to idiots giving their opinion over systems they never understood and never worked as a part of.

Most power production is paid by the users ........Most power companies are Investor owned ....The comments indicate the lack of knowledge concerning who actually owns the systems ......

I worked for the best and learned from the best ........
 

Rockerduck

Well-Known Member
Nov 7, 2022
2,300
1,978
113
70
Marietta, Georgia.
Faith
Christian
Country
United States
Neither of you ever worked in the power industry did you? Your opinions are honestly uninformed. Every opportunity is used to upgrade apparatus when it's necessary. For the most part, the public is paying the freight for the updating. Manufacturers abandoned old poor performing technology for far superior modern technology. Want to get your eyes opened? Walk into a government power producing or distributing meeting and present what's available today The engineers will look at you like they were dropped in from a Flintstones episode. Large transformers are designed and intended to operate for 50 plus years.

Best advice is to stop listening to idiots giving their opinion over systems they never understood and never worked as a part of.

Most power production is paid by the users ........Most power companies are Investor owned ....The comments indicate the lack of knowledge concerning who actually owns the systems ......

I worked for the best and learned from the best ........
Trained electrician and electronics, and power distribution man here. You just said everything I said.
 

Truth7t7

Well-Known Member
Jan 2, 2014
11,864
3,694
113
Faith
Christian
Country
United States
Trump's national emergency declaration is real about modernizing the electric grid
Future electrical demand is going to skyrocket.



America’s electrical grid is in desperate need of investment and modernization. Built largely in the 1960s and 70s it struggles to meet today’s demands for reliability and resilience—let alone the exponential growth expected from new technologies like artificial intelligence, quantum computing, and potentially fusion energy. Power outages are becoming more frequent and severe, as aging infrastructure buckles under the strain of extreme weather events and rising consumption.
There isn't a shortage, it's nothing more than electrical producers propaganda to raise rates

No different than the calls of drought raising water rates, only to keep them there just like tax increases

They can build big power combined cycle skids providing clean efficient electricity in months using natural gas

California for example has been shrinking over the past decade as residents and business is fleeing the State, and yes they want those that have stayed to pick up the tab, it's nothing more than a State Tax on energy, just like gas at the pump
 

Scott Downey

Well-Known Member
Dec 19, 2021
7,926
4,949
113
65
St. Thomas
Faith
Christian
Country
Virgin Islands, U.S.
There isn't a shortage, it's nothing more than electrical producers propaganda to raise rates

No different than the calls of drought raising water rates, only to keep them there just like tax increases

They can build big power combined cycle skids providing clean efficient electricity in months using natural gas

California for example has been shrinking over the past decade as residents and business is fleeing the State, and yes they want those that have stayed to pick up the tab, it's nothing more than a State Tax on energy, just like gas at the pump
Bloom Energy is an example. Can use either NGas or Hydrogen to create lots of electrical power, and the setup is fast in 50 days to producing lots of onsite power at 90% efficiency rate of gas to electricity. Trump is also freeing up regulations to get this going faster.
Bloom's equipment can also reverse the process using electric power to create hydrogen.

And was reading science has discovered a more efficient and cheaper way to create hydrogen at much lower temperatures.


According to a report released this week by Bloom Energy, US data centers will need 55 gigawatts of new power capacity within the next five years.
The report, based on a survey of 100 data center leaders, also shows that 30% of all sites will be using onsite power by 2030. For reference, McKinsey research estimates that there was 25 gigawatts worth of demand in 2024.
McKinsey has similar predictions for power demand growth, estimating that US data centers will have more than 80 gigawatts of demand in 2030.

“This growth is fueled by the continued increase in data, compute and connectivity from digitalization, and cloud migration, as well as the scaling of new technologies—the most important of which is AI,” McKinsey researchers say.

But data centers can only operate if there is sufficient power and the industry is already hitting constraints in some geographies.
According to McKinsey, the time required to get new power connections for data center sites in major hubs like Northern Virginia, California, and Phoenix has already begun to go up. And outside the US, Amsterdam, Dublin and Singapore are among the locations that have placed moratoriums on new data center builds because of a lack of power infrastructure.

The spike in electricity needs is unprecedented, McKinsey wrote, and will be difficult to meet.
In another report released this week, Goldman Sachs also predicts a surge in data center power demand, and expects an increase of 160% by 2030, compared to 2023 levels.
Data center builds typically have timelines of 18 to 24 months, gas and renewable power plans have timelines of three to five years, and new transmission development can take seven to ten years. In fact, it’s the power transmission grid that’s often the biggest constraint, the research firm says, more even than the power generation capacity.

According to a report by Grid Strategies, construction of new high-voltage transmission lines has actually slowed recently, dropping steadily from a peak of 4,000 miles of new high-voltage lines in 2012 to just 55 in 2023.
To meet demands, the DOE estimates that 115,000 miles will be needed by 2040, doubling current grid capacity.
Companies are already planning ahead for shortfalls.

Distributed content platform Akamai Technologies, for example, has increased its data center supply by more than 50% over the past three years.
The company depends heavily on its data center suppliers, according to Todd Lawrence, Akamai’s VP of global data center strategy — and that there’s a potential for data center supply issues in some markets.
To prepare, Akamai regularly communicates with its providers about its needs, Lawrence told Network World, and has three, five, and seven-year plans in place for each market.

“This will help Akamai protect access to critical data center supply in key markets,” he says.
In addition to working with data center providers to ensure long-term access to capacity, enterprises are also casting a wider geographical net, looking towards renewables, and considering fuel cells to power on-prem data centers.
“By leveraging the lowest-cost new builds, such as renewables, alongside energy storage solutions like batteries, they can balance reliability with sustainability,” David Wilson, CEO at Energy Exemplar, an energy simulation platform, told Network World.

There are also renewable options that don’t have the same variability challenges as wind and solar, he adds, such as biomass, green hydrogen — and even small modular reactors.
But it takes time to get renewable power generation up and running, says Aman Joshi, chief commercial officer at Bloom Energy, and renewables have the same transmission challenges as traditional power generation facilities.
That’s why nearly a third of data centers are looking to on-site generation, Joshi said.

Other research backs this up.
According to Frost & Sullivan, the growth of stationary fuel cells deployments is accelerating. Stationary fuel cells are the kind used by data centers and industrial plants, as opposed to mobile ones such as those in cars and trucks.
There were 345 megawatts of new installs in 2023, and an estimated 418 in 2024. This number is projected to increase to 1,420 a year by 2035.

The four biggest players in this market are Bloom Energy, Doosan-HyAxiom, FuelCell Energy and Panasonic, with Bloom in the lead.
“The market has huge potential, given the continued demand for decentralized energy solutions,” says Jonathan Robinson, the firm’s global power and energy research director, in the report. “Manufacturers have strengthened supply chain resilience and are now actively focused on reducing costs.”
Bloom Energy’s Joshi, says that his company is expanding production and doesn’t suffer from the same supply chain constraints as other technologies.

“Our supply chain is very different from conventional gas turbines or wind or batteries, and as a result we don’t use the same raw materials as some of the other technologies use,” he says. “We’re very confident in our ability to scale up.”
 

Scott Downey

Well-Known Member
Dec 19, 2021
7,926
4,949
113
65
St. Thomas
Faith
Christian
Country
Virgin Islands, U.S.

Clean hydrogen in minutes: Microwaves deliver clean energy faster​

Date:January 21, 2025Source:pohang University of Science & Technology (POSTECH)Summary:An interdisciplinary team has developed a groundbreaking technology that addresses key limitations in clean hydrogen production using microwaves. They have also successfully elucidated the underlying mechanism of this innovative process.

As the world shifts away from fossil fuels, clean hydrogen has emerged as a leading candidate for next-generation energy due to its zero carbon emissions. However, existing hydrogen production technologies face significant barriers. Conventional thermochemical methods, which rely on the oxidation-reduction of metal oxides, require extremely high temperatures of up to 1,500°C. These methods are not only energy-intensive and costly but also challenging to scale, limiting their practical application.

To address these challenges, the POSTECH team turned to a familiar yet underutilized energy source: "microwaves"1 energy, the same source used in household microwave ovens. While microwaves are commonly associated with heating food, they can also drive chemical reactions efficiently. The researchers demonstrated that microwave energy could lower the reduction temperature of Gd-doped ceria (CeO2) -- a benchmark material for hydrogen production -- to below 600?, cutting the temperature requirement by over 60 percent. Remarkably, microwave energy was found to replace 75 percent of the thermal energy needed for the reaction, a breakthrough for sustainable hydrogen production.

Another critical advancement lies in the creation of "oxygen vacancies"2, which are defects in the material structure essential for splitting water into hydrogen. Conventional methods often take hours at extremely high temperatures to form these vacancies. The POSTECH team achieved the same results in just minutes at temperatures below 600°C by leveraging microwave technology. This rapid process was further validated with a thermodynamic model, which provided valuable insight into the mechanism underlying the microwave-driven reaction.

Professor Hyungyu Jin stated, "This research has the potential to revolutionize the commercial viability of thermochemical hydrogen production technologies. It will also pave the way for the development of new materials optimized for microwave-driven chemical processes." Professor Gunsu Yun added, "Introducing a new mechanism powered by microwaves and overcoming the limitations of existing processes are major achievements, made possible through the close interdisciplinary collaboration of our research team."

This study was supported by the Circle Foundation's Innovative Science and Technology Program, the Ministry of Science and ICT's Mid-Career Researcher Program, POSTECH's Basic Science Research Institute, and the Ministry of Trade, Industry, and Energy.

Notes:

1. Microwaves



Electromagnetic waves with frequencies ranging from 300 MHz to 300 GHz. They are commonly used to transmit energy or heat materials in wireless communication, radar systems, and microwave ovens.

2. Oxygen vacancy

A state in which an oxygen atom is missing from within a material, leaving behind an empty site. This vacancy can play a critical role in enhancing electron flow or chemical reactivity.
 

bluedragon

Well-Known Member
Aug 7, 2021
2,122
1,591
113
70
Birmingham, Al
Faith
Christian
Country
United States
Trained electrician and electronics, and power distribution man here. You just said everything I said.
The problem has been the idiocy of the Democratic Party. Selling their souls for an energy system that is not reliable nor dependable. To complicate that ideology, they have to lie about everything they do. We were solving door issues on transformers at the Oregon Gorge. Two University of Oregon Coeds were working on a class project during the summer. They were counting bird kills. Their report was going to the Fed ...The actual counts were being changed. If you were on the site ....you can hear the bird impacts on the propellers. Our problem was not Bird impacts. Because we were on a ranch ......and our attention was cattle and transformers, our problem was cattle using cooling fins to scratch their back. They were breaking welds and causing leaks.

Besides being unreliable and inconsistent my complaint is the owners are not required to clean up their own mess. The contracts should be written to force the owner to clean up their mess. Remove the towers after the farm fails.

We learned the best use of a wind tower while up on that ridge. There are no trees up there. Early in the morning, we would arrive to see the black angus lined up in the shade of the tower. They would follow the shade like a sundial. Shade trees for cows.

First Solar was worse ......Obama's pet project. Still wondering how much money they were sending Michelle. Or is it Michael?
 

bluedragon

Well-Known Member
Aug 7, 2021
2,122
1,591
113
70
Birmingham, Al
Faith
Christian
Country
United States
I took a trip to PREPA. For those who don't know who that is ......Puerto Rico Electric Power Authority. My trip was to collect an over due check for $450,000 . This is what takes place ......Nepotism ....New Governor, new Power Board. All family members. I sat and watched 14 people sign the same check. We started filling orders for new transformers again.

The next day, we went and toured the PREPA System ......Spaghetti. No reason for what I saw. When the hurricanes hit .......the result was exactly as I expected. Yet we have a group of power hungry idiots that want Puerto Rico as a 51st state. The only hope is that the US teams that took the bait and rebuilt the mess .......made it look like the typical US City system.